Geotechnical engineering connects ground conditions with the proposed works. NF P 94-500, November 2013, listed as current by AFNOR when checked on 19 October 2026, defines design, construction and diagnostic assignments. G2 PRO is a phase of G2; G5 addresses a specific question.

Référence AFNOR · NF P 94-500

Assignment / phaseWhenPurpose
G1 · ES / PGCEarly stageIdentify site characteristics, initial risks and possible construction principles.
G2 AVPPreliminary designCompare feasible geotechnical solutions for the project.
G2 PROProject designDevelop and substantiate the geotechnical design.
G2 DCE / ACTTenderingPrepare geotechnical tender information and contribute to bid assessment.
G3Construction · contractorDevelop execution studies and monitor geotechnical construction.
G4Construction · ownerSupervise the execution studies and their geotechnical monitoring.
G5Specific questionInvestigate a defined geotechnical issue on a project or existing structure.

Synthèse : tableaux de classification, Géorisques.

G2 AVP and G2 PRO: different design stages

G2 AVP alone is not a complete G2 assignment. PRO develops the selected solution; DCE/ACT supports tendering. Project information must keep pace: layouts, levels, structural loads and neighbouring structures.

G3 and G4: supporting construction

G3 acts for the contractor, while G4 acts for the owner. Their roles are complementary. Define information exchanges, hold points and how deviations will be handled.

G5 is a targeted diagnostic

A question concerning an existing element or observed damage may call for G5. Its scope must be explicit. If remedial works are proposed, the relevant design and execution studies still need to be arranged; G5 does not replace them.

DIS and the geotechnical specialist

DIS coordinates the brief, schedule and interfaces between geotechnical engineers, structural engineers, architects and contractors. The appointed specialist performs investigations, interpretation and geotechnical justification. Assemble drawings, loads, existing studies and the precise question before consulting. Select the scope with the specialist rather than treating a borehole price as a complete study.